Northumberland County Councils 3 proposed models for Education in the West
Model a
Maintain existing hybrid model: 3 tier Hexham, 2 and 3 tier Haydon Bridge but close HBHS
“HMS and QEHS might relocate or expand existing buildings, either on one of the existing schools’ current sites or to another new site”
- Years 7 & 8 from Haydon Bridge partnership feed into HMS
- Close 9/32 schools
- HBHS
- close on 31st August 2019
- 8 first/primary schools
- close on 31st August 2019
- HBHS
- QEHS becomes 11.6 form entry
- 350 pupils per year
- 1550 capacity
- HMS becomes 7 form entry at year 7
- 150 pupils per year in years 5 & 6
- 210 pupils per year in years 7 & 8
- 720 capacity
“HMS and QEHS might relocate or expand existing buildings, either on one of the existing schools’ current sites or to another new site”
- Temporary accommodation provided from Sept 2019 until new build on new site in Hexham is completed Sept 2022
Model b
Change to 2 tier system of primaries and one secondary school
“A brand new QEHS building would be built in Hexham with a target opening date of 2022”.
- Close 14/32 schools
- HBHS
- close on 31st August 2019
- 5 middle schools
- no year 5 from Sept 2019
- close 31st Aug 2020
- 8 first/primary schools
- close on 31st August 2019
- HBHS
“A brand new QEHS building would be built in Hexham with a target opening date of 2022”.
- Temporary accommodation required at HMS/QEHS until September 2022 for QEHS new build on a new site in Hexham
- 350 students per year
- 2250 student capacity
Model c
Hybrid model: 3 tier Hexham, 2 tier Haydon Bridge with an “all through” age 3-16 school in Haydon Bridge
“An all through 9-18 campus would be established through the co-location of QEHS and HMS. It would be proposed that the two schools would relocate to new buildings on the site of the existing buildings or a new site.”
- Close 10/32 schools
- 2 middle schools
- no year 5 from Sept 2019
- close 31st Aug 2020
- 8 first/primary schools
- close on 31st August 2019
“An all through 9-18 campus would be established through the co-location of QEHS and HMS. It would be proposed that the two schools would relocate to new buildings on the site of the existing buildings or a new site.”
- New build for an age 9 -18 QEHS by Sept 2022